To improve upon our networking infrastructure, IT has created a multi-year project that involves the replacement of all Core Switches and CAT5 cabling.


Project Beginning:

August 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

All

Completed Buildings or Departments:

none


Estimated Completion Date: 7/31/2019




Wireless Network Upgrade


In an effort to provide reliable wireless coverage, IT has created a multi-year project that involves the replacement of all WiFi Access Points and Controllers.


Project Beginning:

June 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

All

Completed Buildings or Departments:

none


Estimated Completion Date: 7/31/2019




IT Security Plan


IT is enhancing its security strategy to adequately protect and reduce risks associated with people, processes, and technologies.


Project Beginning:

May 2017


Current Status

50%


Current project phase could affect the following

Buildings or Departments:

none

Completed Buildings or Departments:

none


Estimated Completion Date: 1/5/2018




Data Warehouse and Reporting Platform


IT will identify and implement necessary reporting and data analysis tools for improved utilization of data.


Project Beginning:

May 2017


Current Status

50%


Current project phase could affect the following

Buildings or Departments:

none

Completed Buildings or Departments:

none


Estimated Completion Date: 5/8/2019




Office 2016 Rollout


In an effort to use the features and functionality that Office 2016 offers, IT will upgrade all offices, classrooms, and labs.


Project Beginning:

November 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

All Buildings

Completed Buildings or Departments:

none


Estimated Completion Date: 2/28/2018




Telephone System


In an effort to update our current telephone system, IT will be replacing our PBX system with VOIP, a newer, feature-rich technology.


Project Beginning:

August 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

All

Completed Buildings or Departments:

none


Estimated Completion Date: 9/30/2019




Banner 9 Upgrade


In an effort to use the features and functionality that Banner 9 offers, IT will perform an upgrade to the current Banner system.


Project Beginning:

October 2016


Current Status

75%


Current project phase could affect the following

Buildings or Departments:

none

Completed Buildings or Departments:

none


Estimated Completion Date: 3/16/2018




Zoom Training and Best Practices


IT will provide information and training on Zoom, an alternative method of class delivery.


Project Beginning:

October 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

none

Completed Buildings or Departments:

none


Estimated Completion Date: 1/12/2018




Guest Wireless


IT is developing a Guest Access system for the Wireless Network.


Project Beginning:

November 2017


Current Status

10%


Current project phase could affect the following

Buildings or Departments:

All

Completed Buildings or Departments:

Scully


Estimated Completion Date: 1/1/2020